- The base is installed with clips side panels are screwed into studs.
- Showerhead rough-in installed at 80” AFF.
- Handicap shower is installed where needed, per panel.
- Concrete is poured under the base.
- Plumbing blocking is flush with the wall unless tiled. Tiled wall blocking is set 1 1/4" back.